A general contractor subcontracts electrical work on a commercial building. The electrical subcontractor must be licensed as what tier in South Carolina?
Correct Answer
A) Tier III electrical
Commercial electrical work requires a Tier III electrical contractor license regardless of the project value in South Carolina.
Why This Is the Correct Answer
South Carolina's contractor licensing system requires Tier III electrical licensing for all commercial electrical work. This is the highest electrical tier and reflects the complexity, safety requirements, and code knowledge needed for commercial projects. The requirement applies regardless of the project's dollar value.
Why the Other Options Are Wrong
Option B: Tier II electrical
Tier II electrical licensing is appropriate for residential work but is not sufficient for commercial projects. Using a Tier II subcontractor on commercial work would put the general contractor and subcontractor in violation of SC licensing law.
Option C: Any tier depending on project value
Project value does not determine the required electrical tier in South Carolina. The type of construction (commercial vs. residential) determines the tier requirement, not the contract amount.
Option D: Tier I electrical
Tier I is the lowest electrical tier and covers the most limited scope of work. It is not acceptable for commercial electrical subcontracting.
Memory Technique
Commercial = Top Tier. 'Commercial' and 'Tier III' both represent the highest level. Think: 'Big buildings need the best license β Tier III.' Tier I and II stay residential.
More South Carolina Questions
What is the maximum contract value a Tier 1 residential contractor can undertake in South Carolina?
Under South Carolina law, a contractor discovers a material defect in their work 6 months after project completion. The owner demands immediate correction. What is the contractor's legal obligation?
A contractor has 15 employees and annual payroll of $780,000. The workers compensation rate is $4.25 per $100 of payroll. What is the annual premium?
According to SC building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A subcontractor completes $25,000 of electrical work but is not paid by the general contractor. The general contractor was paid by the owner. What is the subcontractor's lien priority against the property?
A contractor receives a stop work order from the building official. Work continues for 3 additional days before stopping. What penalty applies per South Carolina building codes?
Under South Carolina workers compensation law, which of the following employees would be exempt from coverage requirements?
Under South Carolina contractor licensing law, how many hours of continuing education are required annually for license renewal?
A Class B contractor wants to bid on a $750,000 commercial project. What must the contractor do to be eligible?
A contractor's license expires on June 30th. They submit renewal application and fees on July 15th. What additional penalty must they pay?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor fails to provide preliminary notice for a mechanics lien in South Carolina. The work was completed on March 15th, and the general contractor was paid on April 1st. What is the last day to file the lien?
Next Question
Which insurance coverage amount is required for a South Carolina Tier 2 commercial contractor?
