A contractor fails to provide preliminary notice for a mechanics lien in South Carolina. The work was completed on March 15th, and the general contractor was paid on April 1st. What is the last day to file the lien?

Correct Answer

C) May 1st

Without preliminary notice, subcontractors must file within 30 days of the general contractor's final payment, which would be May 1st.

Answer Options
A
June 1st
B
May 15th
C
May 1st
D
April 15th

Why This Is the Correct Answer

Without preliminary notice, subcontractors must file within 30 days of the general contractor's final payment, which would be May 1st.

Was this explanation helpful?

More sc-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.