A contractor's bond claim is filed for $8,000 in Nevada. The contractor's bond amount is $15,000. If multiple claims total $25,000, how much will this specific claimant receive from the bond?

Correct Answer

C) $4,800

When claims exceed the bond amount, payments are prorated. $8,000 ÷ $25,000 × $15,000 = $4,800.

Answer Options
A
$15,000
B
$8,000
C
$4,800
D
$6,000

Why This Is the Correct Answer

When total claims against a bond exceed the bond's face value, each claimant receives a prorated share. The formula is: (Individual Claim ÷ Total Claims) × Bond Amount. Here: $8,000 ÷ $25,000 = 0.32 (32%), and 32% × $15,000 = $4,800. This ensures all claimants are treated equitably.

Why the Other Options Are Wrong

Option A: $15,000

$15,000 is the total bond amount, not what a single claimant receives. Paying one claimant the full bond would be unfair to other valid claimants and is not how proration works.

Option B: $8,000

$8,000 is the full amount of the claim, which the claimant would receive only if total claims did not exceed the bond. Since claims exceed the bond, full payment is not possible.

Option D: $6,000

$6,000 appears to be based on an incorrect calculation (perhaps $8,000 ÷ $25,000 × $15,000 computed incorrectly, or a $15,000 ÷ $25,000 ratio applied to something else). The correct proration yields $4,800.

Memory Technique

Use the 'pie slice' method: the bond is a pie. Each claimant's slice is proportional to their piece of the total claims. This claimant owns 8/25 of the total claims, so they get 8/25 of the $15,000 pie.

Was this explanation helpful?

More Nevada Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.