A contractor receives a Notice of Disciplinary Action from NSCB. How many days does the contractor have to request a hearing?
Correct Answer
B) 15 days
Under NSCB procedures, contractors have 15 days from receipt of a Notice of Disciplinary Action to request a hearing.
Why This Is the Correct Answer
Under NSCB (Nevada State Contractors Board) procedures, a contractor who receives a Notice of Disciplinary Action has 15 days from the date of receipt to submit a written request for a hearing. Failing to request a hearing within this window results in the disciplinary action becoming final by default.
Why the Other Options Are Wrong
Option A: 30 days
30 days is a common deadline in other administrative and legal contexts, making it a tempting choice. However, NSCB uses a shorter 15-day window for hearing requests, placing urgency on the contractor to act quickly.
Option C: 10 days
10 days is too short and does not match NSCB procedure. This might be confused with timelines in other administrative processes but is not the correct hearing request window.
Option D: 20 days
20 days is close to the correct answer but still wrong. The NRS 108 preliminary notice deadline (20 days) may cause candidates to transpose that figure here. The NSCB hearing request window is specifically 15 days.
Memory Technique
15 days = half a month to respond to discipline. Think of it as a 'two-week-plus-one' deadline β act fast or the board's decision sticks. '15' rhymes with 'act quick before it hits.'
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An employee is injured on a Nevada construction site. The contractor's workers' compensation coverage has lapsed. What is the contractor's potential liability?
Next Question
According to Nevada workers' compensation requirements, which of the following contractors is exempt from carrying workers' compensation insurance?