A contractor is building a home in a tsunami evacuation zone on the Big Island. According to Hawaii Building Code, what additional structural requirement applies?

Correct Answer

D) All utilities must be elevated above base flood elevation

In tsunami evacuation zones, Hawaii Building Code requires all utilities and mechanical equipment to be elevated above the base flood elevation to prevent damage and contamination.

Answer Options
A
Structure must be designed for breakaway lower level
B
Building must include emergency escape routes
C
Foundations must extend to bedrock
D
All utilities must be elevated above base flood elevation

Why This Is the Correct Answer

Hawaii Building Code requires that all utilities and mechanical equipment be elevated above the base flood elevation (BFE) in tsunami and flood hazard zones. This prevents utility damage during inundation and reduces contamination risk (e.g., sewage, fuel) that could compound disaster impacts.

Why the Other Options Are Wrong

Option A: Structure must be designed for breakaway lower level

Breakaway lower levels are a FEMA-required feature for structures built in coastal A and V flood zones, not a blanket requirement for all tsunami evacuation zone construction under Hawaii Building Code. This is a plausible but incorrect option.

Option B: Building must include emergency escape routes

Emergency escape routes are a general life-safety requirement and are not a special additional structural requirement specifically triggered by tsunami zone classification. This option confuses occupancy/egress rules with hazard-zone construction rules.

Option C: Foundations must extend to bedrock

Extending foundations to bedrock is not universally required by Hawaii Building Code for tsunami zones. Bedrock depth varies enormously across the Big Island, and such a blanket rule is not codified. This is a distracter that sounds geologically plausible.

Memory Technique

Tsunami = water rises. So everything that could be harmed or cause harm when wet (utilities, mechanical) must rise above the base flood elevation. Think: 'Water rises, so utilities rise.'

Was this explanation helpful?

More Hawaii Questions

A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?

A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?

Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?

What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?

Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?

A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?

During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:

You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?

According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?

A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.