A contractor is bidding on a public works project subject to prevailing wage. The project duration is 180 days. What ongoing compliance requirement must be met throughout the project?

Correct Answer

A) Submit certified payroll records weekly

Public works projects require contractors to submit certified payroll records weekly to the awarding agency, documenting compliance with prevailing wage requirements for all workers on the project.

Answer Options
A
Submit certified payroll records weekly
B
File quarterly compliance reports
C
Conduct monthly wage surveys
D
Post prevailing wage rates at the job site

Why This Is the Correct Answer

California Labor Code Section 1776 requires contractors and subcontractors on public works projects to submit Certified Payroll Records (CPR) weekly to the awarding body. These records document each worker's name, address, classification, hours worked, wage rates paid, and deductions — verifying compliance with prevailing wage laws for every week of the project.

Why the Other Options Are Wrong

Option B: File quarterly compliance reports

Quarterly compliance reports are not the standard for public works prevailing wage. The requirement is weekly certified payroll records, not quarterly filings. Quarterly reporting would leave months of non-compliance undetected.

Option C: Conduct monthly wage surveys

There is no requirement for contractors to conduct monthly wage surveys. Prevailing wage rates are determined by the Department of Industrial Relations (DIR) through periodic surveys — contractors must pay those predetermined rates, not research them themselves.

Option D: Post prevailing wage rates at the job site

While posting prevailing wage rates at the job site is a required notice (Labor Code Section 1773.2), it is a one-time or periodic posting obligation, not the primary ongoing compliance mechanism. The weekly certified payroll submission is the core recurring requirement.

Memory Technique

Public works = weekly paperwork. Every week on a prevailing wage job, a Certified Payroll Record must be submitted. Think: 'Pay day, report day — every week, no delay.'

Was this explanation helpful?

More California Questions

A contractor is bidding on a public works project in Los Angeles County with a contract value of $2,000,000. The prevailing wage determination shows carpenter wages at $45.50 per hour. What additional amount must be paid for health and welfare benefits?

A construction company has 15 employees working on a project. One employee suffers a work-related injury. Under California law, what is the primary difference between Cal/OSHA and federal OSHA jurisdiction?

A contractor employs 8 workers and pays total wages of $480,000 annually. If the Unemployment Insurance (UI) tax rate is 3.4% on the first $7,000 of each employee's wages, what is the total annual UI tax owed?

Under Cal/OSHA regulations, what is required when a construction site has a trench excavation deeper than 5 feet?

A public works project requires certified payroll records. The prevailing wage for an electrician is $52.75 per hour with $18.50 in fringe benefits. If an electrician works 8 hours, what is the total prevailing wage obligation?

On a prevailing wage project, a carpenter's regular rate is $28/hour, but the prevailing wage is $35/hour with $8/hour in benefits. What must the contractor pay if the carpenter already receives $6/hour in benefits?

A California contractor has quarterly payroll of $85,000. What is the State Disability Insurance (SDI) withholding amount if the current SDI rate is 0.9% and the wage base limit is $153,164 annually?

Under California law, which statement about business entity liability is CORRECT?

XYZ Contracting LLC has 8 employees in California. An employee is injured on the job and requires medical treatment costing $15,000. The company has no workers' compensation insurance. What is XYZ's potential liability?

A general contractor subcontracts electrical work to an LLC. The electrician works exclusively for this contractor, uses the contractor's materials, and follows the contractor's daily schedule. Under AB5, this relationship is likely:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.