A contractor in North Carolina has 8 employees with a total annual payroll of $320,000. If the workers' compensation rate is $2.85 per $100 of payroll, what is the annual premium?
Correct Answer
C) $9,120
Annual premium = ($320,000 ÷ $100) × $2.85 = 3,200 × $2.85 = $9,120
Why This Is the Correct Answer
$9,120 is correct. The formula is: ($320,000 ÷ $100) × $2.85 = 3,200 × $2.85 = $9,120. The number of employees is irrelevant — workers' comp premiums are based on payroll, not headcount.
Why the Other Options Are Wrong
Option A: $8,320
$8,320 may result from an arithmetic error, such as using an incorrect divisor or applying the rate incorrectly. It does not match the correct formula result.
Option B: $9,920
$9,920 is a common distractor that might result from using a slightly higher base number. It is $800 above the correct answer and suggests a calculation error in the payroll base.
Option D: $8,640
$8,640 may result from using a different payroll figure or rate in the calculation, such as rounding the payroll units incorrectly.
Memory Technique
Workers' comp formula: Payroll ÷ 100 × Rate = Premium. Write it as (P/100) × R. For this problem: ($320,000/100) × $2.85 = 3,200 × 2.85 = $9,120.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000: