A contractor in Charlotte is building a 2,400 sq ft single-family home. The foundation inspection fails due to improper reinforcement placement. According to NC building codes, what must happen before concrete placement can resume?
Correct Answer
D) Correct the deficiencies and request re-inspection
NC building codes require that all deficiencies noted in failed inspections must be corrected and a re-inspection must be requested and passed before work can continue.
Why This Is the Correct Answer
NC building codes (based on the IBC/IRC adopted statewide) require that when an inspection fails, the contractor must correct all noted deficiencies and then request a re-inspection. Work cannot proceed until the re-inspection is completed and a passing result is issued. This ensures code compliance is verified before covering up the work.
Why the Other Options Are Wrong
Option A: Hire a structural engineer to approve the work
Hiring a structural engineer to approve the work is not the code-required path after a failed inspection. The building inspector — not a private engineer — has authority to approve the work to proceed. A structural engineer may be involved in designing corrective measures, but the inspector must still re-inspect and approve.
Option B: Wait 24 hours and proceed with placement
Waiting 24 hours and proceeding is not a valid option. There is no time-based exception in the code; the failed inspection remains in effect until a passing re-inspection is issued.
Option C: Submit revised structural drawings only
Submitting revised structural drawings alone is insufficient. Drawings are documents; the actual physical work must be corrected and then inspected in the field before concrete can be placed.
Memory Technique
Failed inspection = Fix then Re-inspect. The sequence is always: Correct → Request re-inspection → Get approval → Proceed. No shortcuts, no waiting periods, no paperwork substitutes.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000: