A contractor files a lien for $22,000 but later settles for $18,000. Under NRS 108, what happens to the recorded lien?
Correct Answer
A) It remains at $22,000 until formally released
Under NRS 108, recorded liens remain at their original amount until formally released, regardless of settlement amounts.
Why This Is the Correct Answer
Option A is correct. Under NRS 108, a recorded mechanic's lien remains on title at its original filed amount until it is formally released through a lien release document recorded in the county recorder's office. The settlement of the underlying debt for a lesser amount does not automatically modify or discharge the lien of record.
Why the Other Options Are Wrong
Option B: It automatically reduces to $18,000
The lien does not automatically reduce to $18,000 when a settlement is reached. Liens are instruments recorded against real property; they can only be modified or discharged through formal recorded instruments, not through a private settlement agreement alone.
Option C: It becomes void after settlement
The lien does not become void upon settlement. Settlement resolves the debt between the parties, but the lien encumbering the property remains until a formal lien release is recorded.
Option D: It must be released and re-filed for $18,000
While releasing and re-filing might seem logical, NRS 108 does not require or authorize re-filing the lien for the reduced amount. The original lien remains until it is formally released; a new lien for $18,000 would be an entirely separate filing with its own priority date issues.
Memory Technique
Think of a lien like a lock on a door β settling the argument doesn't unlock the door. You need the formal key (a recorded lien release) to remove it. The amount stays at $22,000 until the release is recorded.
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?