A contractor files a lien for $22,000 but later settles for $18,000. Under NRS 108, what happens to the recorded lien?

Correct Answer

A) It remains at $22,000 until formally released

Under NRS 108, recorded liens remain at their original amount until formally released, regardless of settlement amounts.

Answer Options
A
It remains at $22,000 until formally released
B
It automatically reduces to $18,000
C
It becomes void after settlement
D
It must be released and re-filed for $18,000

Why This Is the Correct Answer

Option A is correct. Under NRS 108, a recorded mechanic's lien remains on title at its original filed amount until it is formally released through a lien release document recorded in the county recorder's office. The settlement of the underlying debt for a lesser amount does not automatically modify or discharge the lien of record.

Why the Other Options Are Wrong

Option B: It automatically reduces to $18,000

The lien does not automatically reduce to $18,000 when a settlement is reached. Liens are instruments recorded against real property; they can only be modified or discharged through formal recorded instruments, not through a private settlement agreement alone.

Option C: It becomes void after settlement

The lien does not become void upon settlement. Settlement resolves the debt between the parties, but the lien encumbering the property remains until a formal lien release is recorded.

Option D: It must be released and re-filed for $18,000

While releasing and re-filing might seem logical, NRS 108 does not require or authorize re-filing the lien for the reduced amount. The original lien remains until it is formally released; a new lien for $18,000 would be an entirely separate filing with its own priority date issues.

Memory Technique

Think of a lien like a lock on a door β€” settling the argument doesn't unlock the door. You need the formal key (a recorded lien release) to remove it. The amount stays at $22,000 until the release is recorded.

Was this explanation helpful?

More Nevada Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.