A contractor fails to file a mechanic's lien within the required timeframe. The work was substantially completed on March 15th. What was the filing deadline under NC lien law?
Correct Answer
A) July 14th (120 days)
Under NC lien law, a mechanic's lien must be filed within 120 days of substantial completion of the work.
Why This Is the Correct Answer
Under NC lien law, a mechanic's lien must be filed within 120 days of substantial completion of the work.
More nc-supplement Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under NC lien law, a general contractor must provide a 'Notice to Owner' when the contract amount exceeds what threshold?
Next Question
A painting contractor has an annual payroll of $165,000. The workers compensation rate for painting is $6.25 per $100 of payroll. If there's a 15% experience modification factor applied, what is the adjusted annual premium?