A contractor discovers they need to install additional structural supports not shown in the original plans. Under Nevada building codes, what must they do before proceeding?
Correct Answer
A) Obtain revised plans and permits from the building department
Nevada building codes require that structural modifications be properly engineered, documented in revised plans, and approved through the permit process before installation.
Why This Is the Correct Answer
Nevada building codes require that any structural modifications be properly documented in revised plans, reviewed by the building department, and approved with a revised permit before work proceeds. Structural changes affect the safety and integrity of the building and cannot be made without proper engineering documentation and official approval.
Why the Other Options Are Wrong
Option B: Proceed with work and document changes
Proceeding with work and documenting changes afterward violates Nevada building code requirements. Structural modifications require advance approval, not after-the-fact documentation. Working without proper permits on structural changes is a code violation.
Option C: Notify the owner and continue working
Notifying the owner is good communication practice but does not satisfy the legal requirement under Nevada building codes. The owner's knowledge of the change does not substitute for the required permit process with the building department.
Option D: Stop work until the architect approves changes
Stopping work until the architect approves changes alone is insufficient. While architect review may be part of the process, the permit must ultimately be obtained from the building department — not just approved by the architect. The building department issues the official permit.
Memory Technique
For structural changes: think 'Revise, Review, Permit, then Proceed.' Any change to the structural plans requires revised plans → building department review → new/revised permit → only then can work continue. Never proceed on a structural change without a permit.
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?