A contractor discovers asbestos-containing materials during renovation of a commercial building in North Carolina. The project involves removing 500 square feet of asbestos floor tiles. What notification requirement applies?

Correct Answer

D) 10-day advance notification to NC DEQ

NC environmental regulations require 10-day advance notification to DEQ for asbestos removal projects exceeding 160 square feet of non-friable materials.

Answer Options
A
Notification only if friable materials
B
24-hour emergency notification
C
No notification required
D
10-day advance notification to NC DEQ

Why This Is the Correct Answer

The correct answer is D (10-day advance notification to NC DEQ). North Carolina environmental regulations implementing the National Emission Standards for Hazardous Air Pollutants (NESHAP) require contractors to notify the NC Department of Environmental Quality (DEQ) at least 10 working days before beginning asbestos demolition or renovation projects that meet threshold quantities. Floor tiles are non-friable materials; the threshold for non-friable materials is 160 square feet, which this 500 sq ft project clearly exceeds.

Why the Other Options Are Wrong

Option A: Notification only if friable materials

Notification only if friable materials is incorrect. NC NESHAP regulations apply to both friable and non-friable asbestos-containing materials once the quantity threshold is exceeded. Floor tiles are non-friable, but at 500 sq ft (well above the 160 sq ft threshold), notification is still required.

Option B: 24-hour emergency notification

24-hour emergency notification is not the standard requirement for planned asbestos removal projects. A 24-hour notification would only apply in genuine emergency demolition situations (e.g., a structure that poses an imminent safety hazard). Planned renovations require the full 10-day advance notice.

Option C: No notification required

No notification required is incorrect. At 500 square feet of asbestos-containing floor tiles, the project far exceeds the 160 square foot threshold for non-friable materials. Notification to NC DEQ is mandatory before work begins.

Memory Technique

Remember '10 days to DEQ' for asbestos — ten fingers, ten days, tell the DEQ. The threshold trigger for non-friable materials is 160 sq ft (think: a 10'×16' room floor). This project at 500 sq ft is clearly above threshold, so the full 10-day notice applies.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.