A contractor begins work on a private construction project in Louisiana on March 15th. Under the Private Works Act, what is the deadline to file a statement of claim to preserve lien rights?
Correct Answer
B) September 15th
Under Louisiana's Private Works Act, a statement of claim must be filed within 180 days (6 months) from the last day work was performed to preserve lien rights.
Why This Is the Correct Answer
Under Louisiana's Private Works Act, a statement of claim must be filed within 180 days (6 months) from the last day work was performed to preserve lien rights.
More la-supplement Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A subcontractor completes electrical work but the general contractor hasn't paid. Under Louisiana lien law, who can the subcontractor file a lien against?
Next Question
A subcontractor completes electrical work worth $12,500 on March 15th. The general contractor was paid by the owner on March 30th but hasn't paid the subcontractor. Under Louisiana law, when does the subcontractor's lien rights expire?