A building site has been classified as having Type F soil (poor soil requiring site-specific analysis). According to CBC seismic provisions, what additional requirement must be met before construction can begin?

Correct Answer

B) Conduct site-specific seismic response analysis

CBC requires site-specific seismic response analysis for Type F soils, which include soils vulnerable to potential failure or collapse under seismic loading, such as liquefiable soils and highly plastic clays.

Answer Options
A
Increase foundation depth by 50%
B
Conduct site-specific seismic response analysis
C
Install deep pile foundations only
D
Use only mat foundations

Why This Is the Correct Answer

CBC requires a site-specific seismic response analysis before construction can begin on Site Class F soils. Standard spectral response values used for other site classes cannot reliably characterize the amplification behavior of these problematic soils (liquefiable layers, highly plastic clays, peats, sensitive soils). A geotechnical engineer must model actual site response under seismic loading to develop appropriate design parameters.

Why the Other Options Are Wrong

Option A: Increase foundation depth by 50%

Increasing foundation depth by 50% is an oversimplified rule-of-thumb with no basis in CBC's Site Class F requirements. Foundation depth alone does not address the seismic response amplification that makes Site Class F soils dangerous.

Option C: Install deep pile foundations only

Installing deep pile foundations only may ultimately be required based on the site-specific analysis, but it is not the first mandatory step. The analysis must come before any foundation decisions β€” you need the data to determine the appropriate foundation system.

Option D: Use only mat foundations

Using only mat foundations is not what CBC specifies. Mat foundations may be inappropriate for many Site Class F conditions. Again, the foundation type is determined after the required site-specific analysis, not prescribed categorically by the site class designation itself.

Memory Technique

Site Class F = 'First Analyze.' The F stands for both the soil class and the First step: perform a site-specific seismic analysis before anything else.

Was this explanation helpful?

More California Questions

A contractor is installing shear walls in a residence located in Seismic Design Category D. The engineer's plans call for 15/32-inch structural sheathing with 8d nails at 6 inches on center at panel edges. The contractor wants to substitute 7/16-inch OSB with the same nailing. Is this substitution acceptable?

You are reviewing plans for a mixed-use building where the ground floor will house a restaurant with commercial kitchen equipment. The architect has specified standard residential electrical requirements throughout. What Title 24 compliance issue should you identify?

According to CBC seismic provisions, what is the concept behind the 'strong column, weak beam' design philosophy?

A residence in California has 2,800 sq ft of conditioned space. The HVAC system efficiency is 16 SEER. What is the approximate Title 24 compliance margin compared to the minimum 14 SEER requirement?

You're constructing a foundation on liquefiable soils identified in a California coastal area. The geotechnical report recommends deep foundations. Which option is most commonly specified?

A contractor is installing a heat recovery ventilation (HRV) system to comply with Title 24. The system serves a 2,000 sq ft house with 3 bedrooms. What is the minimum required ventilation rate?

During construction of a basement in sandy soil conditions, you encounter groundwater at 4 feet below grade. The basement extends 8 feet below grade. What is the critical design consideration per CBC?

During a seismic retrofit project, you discover that existing concrete has a compressive strength of 2,200 psi. The engineer specifies new anchor bolts that require 2,500 psi minimum concrete strength. What is the most appropriate action?

What is the maximum allowable notch depth in a 2x10 floor joist per CBC requirements?

You're reviewing plans for a wood-framed structure in seismic design category D. The project calls for a shear wall with 15/32-inch structural sheathing and 8d nails spaced 6 inches on center at panel edges. What is the allowable shear value per the CBC?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.