A building project in Hawaii requires soil treatment for termite protection. The treatment area is 45 ft × 30 ft with application rate of 4 gallons per 10 linear feet. How many gallons of termiticide are needed for the perimeter treatment?

Correct Answer

B) 60 gallons

Perimeter = 2(45 + 30) = 150 linear feet. Treatment needed: 150 ÷ 10 × 4 = 60 gallons.

Answer Options
A
54 gallons
B
60 gallons
C
48 gallons
D
72 gallons

Why This Is the Correct Answer

Step 1: Calculate the perimeter. Perimeter = 2 × (45 + 30) = 2 × 75 = 150 linear feet. Step 2: Apply the rate. 150 linear feet ÷ 10 × 4 gallons = 15 × 4 = 60 gallons. Perimeter (not area) is used because the treatment is applied along the foundation edge, not across the entire slab surface.

Why the Other Options Are Wrong

Option A: 54 gallons

54 gallons likely results from an arithmetic error in the perimeter calculation, such as computing 2 × (45 + 30) incorrectly as 135 linear feet (135 ÷ 10 × 4 = 54). Alternatively, a candidate might use only three sides of the building rather than all four.

Option C: 48 gallons

48 gallons results from using 120 linear feet instead of 150 — a common error where the candidate computes only two sides (45 + 30 = 75, then applies the formula without doubling: 75 ÷ 10 × ... or uses 2 × 30 + 2 × 30 = 120).

Option D: 72 gallons

72 gallons results from using 180 linear feet, which could come from rounding up or using an incorrect dimension. For example, 2 × (45 + 45) = 180 if both long sides are mistakenly used as 45 ft, or from adding extra feet for corners.

Was this explanation helpful?

More Hawaii Questions

A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?

A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?

Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?

What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?

Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?

A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?

During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:

You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?

According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?

A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.