A building permit application fee is calculated at $0.75 per $1,000 of construction value with a minimum fee of $150. What is the permit fee for a project valued at $85,000?
Correct Answer
B) $150.00
The calculated fee would be $85,000 ÷ $1,000 × $0.75 = $63.75, but since this is below the minimum fee of $150, the minimum fee applies.
Why This Is the Correct Answer
The correct answer is B ($150.00) because permit fee calculations must always consider minimum fee requirements. Even though the calculated fee based on construction value is only $63.75, the minimum fee of $150 takes precedence when the calculated amount falls below this threshold. This is a common feature in municipal fee structures to ensure administrative costs are covered regardless of project size.
Why the Other Options Are Wrong
Option A: $63.75
Option D ($637.50) suggests an error in the calculation, possibly multiplying by 10 or using an incorrect rate, and doesn't reflect proper application of the fee structure.
Option C: $637.50
Option C ($212.50) appears to add the calculated fee ($63.75) to the minimum fee ($150), which is incorrect methodology - you apply either the calculated fee OR the minimum fee, whichever is higher.
Memory Technique
Remember 'MIN-WIN' - when the MINimum is higher, the minimum fee WINs over the calculated amount.
Reference Hint
Florida Building Code, Chapter 1 - Scope and Administration, Section on Permits and Fees
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A concrete pour is scheduled for tomorrow, but the weather forecast shows 40% chance of rain. The quality control plan requires no rain during placement and 24 hours after. What should the contractor do?
Next Question
A contractor is working under a cost-plus contract with a 15% fee. If the total allowable project costs are $240,000, what is the contractor's total compensation?
