EstatePass
Contract AdminPermitsmedium20% of exam part

A building permit application fee is calculated at $0.75 per $1,000 of construction value with a minimum fee of $150. What is the permit fee for a project valued at $85,000?

Correct Answer

B) $150.00

The calculated fee would be $85,000 ÷ $1,000 × $0.75 = $63.75, but since this is below the minimum fee of $150, the minimum fee applies.

Answer Options
A
$63.75
B
$150.00
C
$637.50
D
$212.50

Why This Is the Correct Answer

The correct answer is B ($150.00) because permit fee calculations must always consider minimum fee requirements. Even though the calculated fee based on construction value is only $63.75, the minimum fee of $150 takes precedence when the calculated amount falls below this threshold. This is a common feature in municipal fee structures to ensure administrative costs are covered regardless of project size.

Why the Other Options Are Wrong

Option A: $63.75

Option D ($637.50) suggests an error in the calculation, possibly multiplying by 10 or using an incorrect rate, and doesn't reflect proper application of the fee structure.

Option C: $637.50

Option C ($212.50) appears to add the calculated fee ($63.75) to the minimum fee ($150), which is incorrect methodology - you apply either the calculated fee OR the minimum fee, whichever is higher.

Memory Technique

Remember 'MIN-WIN' - when the MINimum is higher, the minimum fee WINs over the calculated amount.

Reference Hint

Florida Building Code, Chapter 1 - Scope and Administration, Section on Permits and Fees

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.