EstatePass
Contract AdminProceduresmedium13% of exam part

A concrete pour is scheduled for tomorrow, but the weather forecast shows 40% chance of rain. The quality control plan requires no rain during placement and 24 hours after. What should the contractor do?

Correct Answer

B) Postpone the pour until weather conditions meet quality requirements

Quality control procedures must be followed to ensure structural integrity. Since the quality control plan specifically requires no rain during and 24 hours after placement, the pour should be postponed to meet these requirements.

Answer Options
A
Proceed with the pour as scheduled
B
Postpone the pour until weather conditions meet quality requirements
C
Reduce the concrete placement area by half
D
Pour concrete and cover with plastic if it rains

Why This Is the Correct Answer

Quality control plans are legally binding specifications that must be followed to ensure structural integrity and code compliance. When a quality control plan explicitly requires no rain during placement and for 24 hours after, this becomes a mandatory requirement, not a suggestion. Proceeding with a 40% chance of rain would violate the established quality standards and could result in compromised concrete strength, surface defects, and potential structural issues. The contractor has a professional and legal obligation to postpone the pour until weather conditions meet the specified requirements.

Why the Other Options Are Wrong

Option A: Proceed with the pour as scheduled

Simply covering with plastic does not adequately protect fresh concrete from rain damage, and this approach still violates the specific quality control plan requirement of no rain during placement and 24 hours after.

Option D: Pour concrete and cover with plastic if it rains

Proceeding with the pour despite a 40% chance of rain directly violates the established quality control plan requirements and puts the structural integrity of the concrete at risk.

Memory Technique

QC = Quality Can't be Compromised - when quality control plans specify weather requirements, they must be followed exactly

Reference Hint

Florida Building Code Chapter 19 - Concrete, ACI 305 Hot Weather Concreting, and project specifications for quality control requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.