A unit price contract specifies $45 per cubic yard for concrete work. The original estimate was 800 cubic yards, but actual quantity used was 950 cubic yards. What is the total payment for concrete work?

Correct Answer

B) $42,750

In a unit price contract, payment is based on actual quantities. 950 cubic yards × $45 per cubic yard = $42,750.

Answer Options
A
$38,250
B
$42,750
C
$47,500
D
$36,000

Why This Is the Correct Answer

In a unit price contract, payment is calculated based on the actual quantities of work performed, not the original estimate. The contractor is paid for the exact amount of materials used or work completed at the predetermined unit rate. Since 950 cubic yards of concrete were actually used at $45 per cubic yard, the total payment is 950 × $45 = $42,750. The original estimate of 800 cubic yards is irrelevant for payment calculation in this contract type.

Why the Other Options Are Wrong

Option A: $38,250

This answer uses an incorrect calculation method, possibly adding the unit price incorrectly or using wrong quantities in the multiplication.

Option C: $47,500

This answer incorrectly uses the original estimated quantity (800 cubic yards) instead of the actual quantity used. The calculation 800 × $45 = $36,000 represents what would have been paid if only the estimated amount was used.

Option D: $36,000

This answer appears to be an average or compromise between the estimated and actual quantities, but unit price contracts don't work this way. Payment must be based solely on actual quantities performed.

Memory Technique

Remember 'ACTUAL = PAYMENT' for unit price contracts. The estimate is just a guess - you get paid for what you actually do, not what you thought you'd do.

Reference Hint

Look up 'Contract Types' or 'Unit Price Contracts' in your Florida Construction Law or Project Management reference materials, typically found in chapters covering contract administration or payment methods.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.