A contract allows escalation only with written supplier proof, but the file has only a phone note. What is missing?
Correct Answer
B) Supplier backup.
The contract clause requires written supplier backup before the escalation adjustment is supported.
Why This Is the Correct Answer
The contract clause requires written supplier backup before the escalation adjustment is supported.
More ca-law-business Questions
An $18,500 patio and door replacement contract is a CA home improvement job. What down payment amount is allowed at signing?
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A Class B contractor's prime contract includes fire sprinkler work classified as C-16. What must the contractor do for that scope?
A Class B contractor includes water-well drilling classified as C-57 in the overall project. What is the correct licensing path?
A registered home improvement salesperson leaves one contractor and begins selling for another. What must be checked?
A subcontractor's license classification does not cover the trade scope being subcontracted. What should the prime do before award?
A progress payment schedule asks the owner to pay for rough plumbing before that phase starts. What is the best contract-admin correction?
A contractor licensed only as Class B wants to self-perform a C-10 electrical-only service call with no other trades. What is the licensing concern?
A Class B contractor subcontracts electrical work to a properly licensed C-10 subcontractor as part of a multi-trade building project. What is the licensing result?
A material supplier on a San Jose remodel serves a preliminary notice on day 31 after first furnishing materials. Under the CA 20-day notice rule, what work period is protected by that late notice?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A sole owner forms a corporation but keeps signing contracts personally and corporately. What should be clarified?
Next Question
A contractor paid tax at a 7.75 percent rate when buying materials, but the jobsite rate is 8.25 percent. The materials cost $20,000. What additional use tax difference should be budgeted?