ca-law-businessContract Requirements & Executionmedium

An owner refuses to sign a completed change order but asks the crew to proceed anyway. What is the safest contract response?

Correct Answer

D) Do not proceed.

Work that changes scope or price should not proceed without the required written authorization.

Answer Options
A
Proceed verbally.
B
Ask supplier to sign.
C
Hide the cost in final.
D
Do not proceed.

Why This Is the Correct Answer

Work that changes scope or price should not proceed without the required written authorization.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.