A homeowner receives preliminary notices from two suppliers. What should the owner do before making the next progress payment?

Correct Answer

B) Compare invoices and payment requests against the preliminary notices and payment schedule.

CSLB lien-prevention guidance advises comparing bills to the payment schedule and preliminary notices before payment.

Answer Options
A
Pay the contractor in full and let the contractor settle with the two suppliers.
B
Compare invoices and payment requests against the preliminary notices and payment schedule.
C
Ignore the preliminary notices since they are only informational mailings with no effect.
D
Withhold all further payment until both suppliers withdraw their preliminary notices.

Why This Is the Correct Answer

CSLB lien-prevention guidance advises comparing bills to the payment schedule and preliminary notices before payment.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.