Temporary cords are daisy-chained across a walkway and several connections lie on wet concrete. What should be corrected?
Correct Answer
D) Electrical setup.
Temporary electrical cords and connections should be routed and protected from wet and traffic hazards.
Why This Is the Correct Answer
Temporary electrical cords and connections should be routed and protected from wet and traffic hazards.
Why the Other Options Are Wrong
Option A: Provide GFCI protection.
Provide GFCI protection. may relate to another site control, but it does not remove or guard the temporary electrical safety exposure being tested.
Option B: Remove cord.
Remove cord. may relate to another site control, but it does not remove or guard the temporary electrical safety exposure being tested.
Option C: Reroute or protect it.
Reroute or protect it. may relate to another site control, but it does not remove or guard the temporary electrical safety exposure being tested.
Memory Technique
If Checking Power can still reach the worker, the control is decoration.
Reference Hint
Study anchor (closed-book): memorize Temporary electrical safety from Cal/OSHA Title 8 Construction Safety Orders; CSLB B General Building. / Cal/OSHA Title 8 temporary wiring and flexible cord safety; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?