Spoil from a trench is placed directly at the edge. What is the best correction?

Correct Answer

B) Keep spoil at least two feet back when using the setback method, with further protection as necessary.

Keep spoil at least two feet back when using the setback method. Section 1541(j)(2) also permits adequate retaining devices or a necessary combination; this does not certify the whole excavation. Source: https://www.dir.ca.gov/title8/1541.html

Answer Options
A
Use it as the only barricade.
B
Keep spoil at least two feet back when using the setback method, with further protection as necessary.
C
Push it into the trench.
D
Stand workers below the spoil pile.

Why This Is the Correct Answer

Keep spoil at least two feet back when using the setback method. Section 1541(j)(2) also permits adequate retaining devices or a necessary combination; this does not certify the whole excavation. Source: https://www.dir.ca.gov/title8/1541.html

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.