The finish crew production forecast uses 0.16 labor-hours per square foot for 840 square feet of work. How many labor-hours are required?

Correct Answer

A) 134.4 labor-hours.

Eight hundred forty square feet times 0.16 labor-hours per square foot equals 134.4 labor-hours.

Answer Options
A
134.4 labor-hours.
B
120 labor-hours.
C
148 labor-hours.
D
168 labor-hours.

Why This Is the Correct Answer

Eight hundred forty square feet times 0.16 labor-hours per square foot equals 134.4 labor-hours.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.