Cement backer board seams in a shower are left untreated before waterproofing and tile. What should be completed?
Correct Answer
D) Seam treatment.
Wet-area tile backer seams should be treated as required before waterproofing and tile cover the substrate.
Why This Is the Correct Answer
Wet-area tile backer seams should be treated as required before waterproofing and tile cover the substrate.
Why the Other Options Are Wrong
Option A: Proceed with the finish work where cement backer board seams in a shower are left untreated before waterproofing and tile, and postpone the product or backing correction.
Proceed with the finish work where cement backer board seams in a shower are left untreated before waterproofing and tile, and postpone the product or backing correction. addresses a neighboring field issue, but not the condition or method control required for tile wet-area detailing.
Option B: Treat the item as a color or trim preference where cement backer board seams in a shower are left untreated before waterproofing and tile, instead of correcting the performance item beneath the visible finish.
Treat the item as a color or trim preference where cement backer board seams in a shower are left untreated before waterproofing and tile, instead of correcting the performance item beneath the visible finish. addresses a neighboring field issue, but not the condition or method control required for tile wet-area detailing.
Option C: Accept the installer's shortcut where cement backer board seams in a shower are left untreated before waterproofing and tile, without verifying the required access or movement detail.
Accept the installer's shortcut where cement backer board seams in a shower are left untreated before waterproofing and tile, without verifying the required access or movement detail. addresses a neighboring field issue, but not the condition or method control required for tile wet-area detailing.
Memory Technique
Tile Wet-Area Detailing method for Checking Shower: condition first, tool second.
Reference Hint
Study anchor (closed-book): memorize Tile wet-area detailing from California Residential Code, California Code of Regulations Title 24. / Title 24 California Residential Code wet-area finish and drainage concepts; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
