A critical-path schedule shows waterproofing inspection must pass before tile can start. What happens if the inspection fails?

Correct Answer

A) Tile start is delayed.

If inspection approval is a predecessor to finish work, failure delays downstream work on that path.

Answer Options
A
Tile start is delayed.
B
Final cleaning starts sooner.
C
Long-lead confirmation.
D
Scope clarification.

Why This Is the Correct Answer

If inspection approval is a predecessor to finish work, failure delays downstream work on that path.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.