A shop drawing shows a different stair rail attachment than the approved structural detail. What is the best interpretation?

Correct Answer

C) Get approval before fabrication.

Shop drawings coordinate fabrication but do not automatically authorize changes to approved design requirements.

Answer Options
A
Product data.
B
Material sample.
C
Get approval before fabrication.
D
Closeout submittal.

Why This Is the Correct Answer

Shop drawings coordinate fabrication but do not automatically authorize changes to approved design requirements.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.