A drawing note says to verify an existing rough opening before ordering a replacement unit. What does that mean for procurement?

Correct Answer

D) Measure before ordering.

The note expressly requires the existing opening to be verified before the replacement is ordered. Measure its actual dimensions and check them against the proposed unit. Requesting an inspection, releasing an order without measurement, or deferring the check to a punch list does not carry out that instruction.

Answer Options
A
Inspection request.
B
Release the order without measuring.
C
Punch-list item.
D
Measure before ordering.

Why This Is the Correct Answer

The note expressly requires the existing opening to be verified before the replacement is ordered. Measure its actual dimensions and check them against the proposed unit. Requesting an inspection, releasing an order without measurement, or deferring the check to a punch list does not carry out that instruction.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.