A critical-path schedule shows framing inspection must pass before windows can be covered by interior finishes. What happens if the inspection fails?
Correct Answer
A) Finish start is delayed.
The stated schedule makes a passed framing inspection a prerequisite for interior finishes. Until that prerequisite is met, those finishes cannot start as scheduled. A submittal or scope clarification does not itself satisfy the failed inspection. This follows the dependency given in the question and does not establish a separate lien or licensing rule.
Why This Is the Correct Answer
The stated schedule makes a passed framing inspection a prerequisite for interior finishes. Until that prerequisite is met, those finishes cannot start as scheduled. A submittal or scope clarification does not itself satisfy the failed inspection. This follows the dependency given in the question and does not establish a separate lien or licensing rule.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
A 420-square-foot resilient floor has a 6% area allowance for waste and a material rate of $4.35 per square foot. Ignoring carton rounding, tax and delivery, what is the material estimate?
Next Question
A beam requires 14 pieces of 2x8 lumber at 12 feet. Using nominal board feet, how many board feet are needed?