Landing joists run in a different direction from the approved support detail. Which structural function must be verified when resolving the discrepancy?
Correct Answer
C) Transfer of landing loads through the joists and connections into adequate supports.
Verify how the landing loads reach the intended supporting members. An altered joist direction can change spans, bearing and connections; resolve the discrepancy with the approved design before acceptance.
Why This Is the Correct Answer
Verify how the landing loads reach the intended supporting members. An altered joist direction can change spans, bearing and connections; resolve the discrepancy with the approved design before acceptance.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
The garage roof face worksheet shows that the roofing material order starts from a 34.25-square estimate and adds 8 percent waste. How many total squares should be planned?
Next Question
A paint scope has 1,200 square feet of wall area and requires two coats. Paint covers 350 square feet per gallon per coat. What is the minimum whole number of gallons needed, with no extra stock or waste allowance?