A roof diaphragm is nailed off before missing roof-to-wall clips are installed at the exterior wall. What is incomplete?
Correct Answer
C) Uplift connection.
A nailed diaphragm does not by itself complete an omitted roof-to-wall uplift connection. Install the specified connectors or an approved alternative detail. Source: https://seblog.strongtie.com/2016/07/select-connector-series-hurricane-tie/
Why This Is the Correct Answer
A nailed diaphragm does not by itself complete an omitted roof-to-wall uplift connection. Install the specified connectors or an approved alternative detail. Source: https://seblog.strongtie.com/2016/07/select-connector-series-hurricane-tie/
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
A mirror is installed in a damp bathroom with unsealed backing exposed to repeated moisture. What concern should be addressed?
Next Question
During open, accessible new-construction rough-in, NM cable is draped loosely through a ceiling cavity with no required securing or support. No wiring-method exception applies. What should be corrected before drywall?