Rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall. What is incomplete?
Correct Answer
C) Uplift load path.
Roof-to-wall clips transfer uplift forces from roof framing into the wall load path.
Why This Is the Correct Answer
Roof-to-wall clips transfer uplift forces from roof framing into the wall load path.
Why the Other Options Are Wrong
Option A: Continue framing where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and wait for drywall to hide the framing defect.
Continue framing where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and wait for drywall to hide the framing defect. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.
Option B: Photograph the condition where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, but close the framing item without correcting the fastening or bearing condition.
Photograph the condition where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, but close the framing item without correcting the fastening or bearing condition. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.
Option D: Treat the item as layout cleanup where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and let a later crew work around the framing condition.
Treat the item as layout cleanup where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and let a later crew work around the framing condition. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.
Memory Technique
The field condition asks; roof uplift connectors answers in work boots for Inspecting Framing.
Reference Hint
Study anchor (closed-book): memorize Roof uplift connectors from California Building Code, California Code of Regulations Title 24. / Title 24 California Building Code roof-to-wall uplift connection; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
People Also Study
Related Study Resources
Previous Question
A written dimension conflicts with a scaled takeoff from a small printed plan. Which should generally control before asking for clarification?
Next Question
The bedroom underlayment worksheet shows that the dry-in material order lists 31 rolls of underlayment, with each roll covering 190 square feet. How many square feet can be covered?
