Rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall. What is incomplete?

Correct Answer

C) Uplift load path.

Roof-to-wall clips transfer uplift forces from roof framing into the wall load path.

Answer Options
A
Continue framing where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and wait for drywall to hide the framing defect.
B
Photograph the condition where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, but close the framing item without correcting the fastening or bearing condition.
C
Uplift load path.
D
Treat the item as layout cleanup where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and let a later crew work around the framing condition.

Why This Is the Correct Answer

Roof-to-wall clips transfer uplift forces from roof framing into the wall load path.

Why the Other Options Are Wrong

Option A: Continue framing where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and wait for drywall to hide the framing defect.

Continue framing where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and wait for drywall to hide the framing defect. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.

Option B: Photograph the condition where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, but close the framing item without correcting the fastening or bearing condition.

Photograph the condition where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, but close the framing item without correcting the fastening or bearing condition. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.

Option D: Treat the item as layout cleanup where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and let a later crew work around the framing condition.

Treat the item as layout cleanup where rafters are installed, but the specified roof-to-wall clips are missing at the exterior wall, and let a later crew work around the framing condition. addresses a neighboring field issue, but not the condition or method control required for roof uplift connectors.

Memory Technique

The field condition asks; roof uplift connectors answers in work boots for Inspecting Framing.

Reference Hint

Study anchor (closed-book): memorize Roof uplift connectors from California Building Code, California Code of Regulations Title 24. / Title 24 California Building Code roof-to-wall uplift connection; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.