An engineered truss is drilled through a web for wiring without a repair detail. What should happen?
Correct Answer
B) Obtain and implement the truss-specific approved repair or replacement direction.
Report the drilled web and obtain design review for that truss and hole. Implement the approved repair or replacement; ordinary joist-hole rules do not automatically apply to trusses. Source: https://kcenter.sbcacomponents.com/resource/sbca-knowledge-center-design-of-truss-repairs-dg-no-2501
Why This Is the Correct Answer
Report the drilled web and obtain design review for that truss and hole. Implement the approved repair or replacement; ordinary joist-hole rules do not automatically apply to trusses. Source: https://kcenter.sbcacomponents.com/resource/sbca-knowledge-center-design-of-truss-repairs-dg-no-2501
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
A roof opening for a skylight cuts rafters and leaves them bearing only on roof sheathing. What framing is needed?
Next Question
A rectangular patio slab measures 20 feet by 24 feet and is uniformly 4 inches thick. What net concrete volume is needed, rounded to the nearest hundredth of a cubic yard before waste?