A shear wall end post is installed, but the hold-down bolts are not tightened before wall cover. What should be completed?
Correct Answer
C) The specified hold-down anchorage and tightening procedure.
Complete the hold-down connection according to its applicable installation detail before concealment. It transfers the specified uplift/overturning reaction; use the required tightening instructions rather than an arbitrary torque. Source: https://www.strongtie.com/products/connectors/wood-construction-connectors/technical-notes/general-notes-for-holdowns-and-tensionties
Why This Is the Correct Answer
Complete the hold-down connection according to its applicable installation detail before concealment. It transfers the specified uplift/overturning reaction; use the required tightening instructions rather than an arbitrary torque. Source: https://www.strongtie.com/products/connectors/wood-construction-connectors/technical-notes/general-notes-for-holdowns-and-tensionties
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?