A roof-to-wall uplift connector shown on the plan is omitted at several rafters. What is missing?

Correct Answer

C) The specified roof-to-wall uplift connection.

The plan calls for a connection carrying roof uplift into the wall system. The omitted connectors leave that specified connection incomplete; a different solution requires an approved design. Source: https://seblog.strongtie.com/2016/07/select-connector-series-hurricane-tie/

Answer Options
A
Only the foundation-to-soil bearing connection.
B
Only the truss web bracing.
C
The specified roof-to-wall uplift connection.
D
Only the deck guard connection.

Why This Is the Correct Answer

The plan calls for a connection carrying roof uplift into the wall system. The omitted connectors leave that specified connection incomplete; a different solution requires an approved design. Source: https://seblog.strongtie.com/2016/07/select-connector-series-hurricane-tie/

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.