A truss is field-cut to fit a mechanical duct without manufacturer or engineer approval. What should happen?
Correct Answer
B) Obtain and implement an approved repair or replacement detail.
Report the altered truss and obtain a specific engineered disposition through the truss manufacturer or designer. Complete the approved repair or replacement before acceptance; a generic field patch is insufficient. Source: https://kcenter.sbcacomponents.com/resource/sbca-knowledge-center-design-of-truss-repairs-dg-no-2501
Why This Is the Correct Answer
Report the altered truss and obtain a specific engineered disposition through the truss manufacturer or designer. Complete the approved repair or replacement before acceptance; a generic field patch is insufficient. Source: https://kcenter.sbcacomponents.com/resource/sbca-knowledge-center-design-of-truss-repairs-dg-no-2501
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
A crew dry-cuts silica-containing concrete indoors with no exposure controls. Which response addresses the dust exposure?
Next Question