A new threshold raises the floor and the bathroom door drags during operation. What should be verified?
Correct Answer
C) Door clearance.
Door clearance should be checked against the finished floor and threshold so the door operates properly.
Why This Is the Correct Answer
Door clearance should be checked against the finished floor and threshold so the door operates properly.
Why the Other Options Are Wrong
Option A: Scribe fit.
Scribe fit. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for the compliance trigger.
Option B: Self-closing action.
Self-closing action. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for the compliance trigger.
Option D: Site conditions.
Site conditions. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for the compliance trigger.
Memory Technique
Good work cannot rewind a missed controlling trigger in Checking Interior.
Reference Hint
Study anchor (closed-book): memorize cited field requirement from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide door installation and clearances; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
