The wallboard delivery worksheet shows a ceiling has 960 square feet of drywall area. Using 4-foot by 8-foot sheets, how many sheets are needed before waste?
Correct Answer
A) 30 sheets.
Each sheet covers 32 square feet. The required quantity is 960 / 32 = 30 sheets.
Why This Is the Correct Answer
Each sheet covers 32 square feet. The required quantity is 960 / 32 = 30 sheets.
Why the Other Options Are Wrong
Option B: 28 sheets total.
28 sheets total. is below the supported result for drywall quantity calculation; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 32 sheets total.
32 sheets total. is above the supported result for drywall quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 34 sheets total.
34 sheets total. is above the supported result for drywall quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to sheet, adjust for covers, then let Estimating Board set the finish line.
Reference Hint
Study anchor (closed-book): memorize Drywall quantity calculation from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide drywall estimating; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?