A stone countertop has a long unsupported overhang beyond the cabinet face. What should be checked?
Correct Answer
C) Support or reinforcement.
Stone overhangs need support within the material and installer limits so cracking or failure is avoided.
Why This Is the Correct Answer
Stone overhangs need support within the material and installer limits so cracking or failure is avoided.
Why the Other Options Are Wrong
Option A: Anchor support.
Anchor support. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for stone and countertop support.
Option B: Anchorage support.
Anchorage support. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for stone and countertop support.
Option D: Bracket plan.
Bracket plan. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for stone and countertop support.
Memory Technique
Stone And Countertop clock for Reviewing Kitchen: party, date, proof, then rights.
Reference Hint
Study anchor (closed-book): memorize Stone and countertop support from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide stone and cabinet coordination; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?