A service receptacle for mechanical equipment is removed from the equipment area during a remodel. What should be checked?
Correct Answer
B) Whether a compliant service receptacle remains available for the equipment.
Verify that the equipment retains a service receptacle meeting 2025 CMC 301.4(2), including location and supply-side connection requirements. Removing the nearby receptacle requires checking the remaining provision; it does not prove that every replacement must occupy the identical location. Source: https://epubs.iapmo.org/2025/CMC/
Why This Is the Correct Answer
Verify that the equipment retains a service receptacle meeting 2025 CMC 301.4(2), including location and supply-side connection requirements. Removing the nearby receptacle requires checking the remaining provision; it does not prove that every replacement must occupy the identical location. Source: https://epubs.iapmo.org/2025/CMC/
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
On a project where the relevant CALGreen finish requirements apply, an adhesive is substituted without VOC documentation. What is the appropriate review?
Next Question
A mirror is installed in a damp bathroom with unsealed backing exposed to repeated moisture. What concern should be addressed?