A 24-volt control coil measures 0 volts while its controller is calling for operation. What should be verified next?

California C-10 exam practice question · Startup, Troubleshooting & Maintenance

A 24-volt control coil measures 0 volts while its controller is calling for operation. What should be verified next?

  • AReplace the branch-circuit breaker with a larger one
  • Trace the complete series control path
  • CBypass every safety switch
  • DIncrease the equipment grounding conductor size

Why B is correct

Zero volts at a commanded coil points to a loss in the control-power path or an open safety/control. Tracing the circuit safely identifies the open point; bypassing safeties or changing unrelated power components is improper.