An HVAC access detail requires a clear 18-inch path above a service panel. A new cable tray reduces it to 12 inches. What is the shortfall relative to the specified detail?

Texas ACR A exam practice question Β· Ventilation

An HVAC access detail requires a clear 18-inch path above a service panel. A new cable tray reduces it to 12 inches. What is the shortfall relative to the specified detail?

  • A12 inches
  • 6 inches
  • C18 inches
  • D30 inches

Where to look it up

Explicit exercise assumptions; not a universal code requirement.

Why B is correct

18 βˆ’ 12 = 6 inches. Resolve the coordination conflict against the actual access detail; the exercise does not invent a universal ceiling clearance.