A furnace installation design explicitly requires 600 cfm of combustion-air supply. Commissioning measures 450 cfm. How much additional airflow is needed to meet that specified target?

Texas ACR A exam practice question · Combustion Air

A furnace installation design explicitly requires 600 cfm of combustion-air supply. Commissioning measures 450 cfm. How much additional airflow is needed to meet that specified target?

  • A50 cfm
  • 150 cfm
  • C450 cfm
  • D1,050 cfm

Where to look it up

Explicit exercise assumptions; not a universal code requirement.

Why B is correct

The shortfall is 600 − 450 = 150 cfm. The target is supplied by this exercise; it is not inferred from furnace input or presented as a universal fuel-gas rule.