EstatePass
Business & FinanceOperationsmedium10% of exam part

Your concrete supplier informs you of a 3-day delay due to equipment breakdown, affecting a pour scheduled for tomorrow. The concrete is for foundation work on the critical path. What is your best course of action?

Correct Answer

A) Source concrete from multiple smaller suppliers immediately

For critical path activities with immediate deadlines, sourcing from multiple suppliers provides the fastest solution. This expediting strategy can often secure the needed materials within the original timeframe, even if it requires coordination with several vendors.

Answer Options
A
Source concrete from multiple smaller suppliers immediately
B
Accept the delay and adjust the project schedule
C
Consider using a different foundation method
D
Negotiate with the supplier for expedited delivery

Why This Is the Correct Answer

When critical path activities face immediate deadlines, sourcing concrete from multiple smaller suppliers is the most effective solution. This strategy allows you to secure the required concrete volume by combining deliveries from several vendors, maintaining the original schedule. Multiple suppliers can often collectively meet demand faster than waiting for a single supplier's equipment repair, preventing costly project delays.

Why the Other Options Are Wrong

Option B: Accept the delay and adjust the project schedule

Changing foundation methods mid-project requires engineering approval, permit modifications, and material reordering. This creates longer delays than the original 3-day concrete delay and introduces unnecessary complexity and costs.

Option D: Negotiate with the supplier for expedited delivery

Simply accepting the delay and adjusting the schedule ignores the critical path impact. Foundation work delays cascade through the entire project timeline, affecting subsequent trades and potentially causing significant cost overruns and contract penalties.

Memory Technique

Remember 'Multiple Suppliers = Multiple Solutions' - when one supplier fails on critical path work, divide and conquer by sourcing from several vendors to meet deadlines.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.