EstatePass
Business & FinanceOperationseasy10% of exam part

In a CPM network, what determines which path becomes the critical path?

Correct Answer

D) The path with the longest total duration

The critical path is the sequence of activities that takes the longest time to complete from project start to finish. This path determines the minimum project duration and cannot be delayed without delaying the entire project.

Answer Options
A
The path with the most activities
B
The path with the most complex activities
C
The path with the highest cost activities
D
The path with the longest total duration

Why This Is the Correct Answer

The critical path in a CPM network is determined solely by the longest total duration from project start to finish. This path represents the minimum time required to complete the entire project, as any delay in activities on this path will directly delay the project completion date. The critical path method calculates the total duration of each possible path through the network and identifies the one with the maximum time as critical.

Why the Other Options Are Wrong

Option A: The path with the most activities

The number of activities in a path does not determine the critical path. A path with fewer activities could still have the longest total duration if those activities take more time individually than the many shorter activities on another path.

Option B: The path with the most complex activities

Cost is not a factor in determining the critical path in CPM analysis. The critical path method focuses exclusively on time duration, not financial considerations. High-cost activities may or may not be on the critical path.

Memory Technique

Use 'CPM = Critical Path = Maximum time' - the word 'Critical' suggests urgency and time pressure, which relates to the longest duration path that controls project completion.

Reference Hint

Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management or project management chapters of your reference materials

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.