Contract AdminPermitsmedium20% of exam part

Your client wants to build a warehouse in an area zoned for residential use. The property is adjacent to an industrial zone. What is the most appropriate first step?

Correct Answer

C) Request a zoning variance or rezoning from the local planning department

A warehouse is not permitted in residential zoning, so a variance or rezoning must be obtained first. This is a prerequisite before any building permits can be issued.

Answer Options
A
Contact the fire department for approval
B
Begin construction and apply for permits later
C
Request a zoning variance or rezoning from the local planning department
D
Apply for a building permit with the current zoning

Why This Is the Correct Answer

Option B is correct because zoning compliance is a fundamental prerequisite before any construction can begin. A warehouse is a commercial/industrial use that is not permitted in residential zoning, regardless of adjacent zoning. The local planning department has authority over zoning matters and must approve either a variance (exception to current zoning) or a rezoning (changing the zoning classification) before any building permits can be considered or issued.

Why the Other Options Are Wrong

Option B: Begin construction and apply for permits later

While fire department approval may be required later in the permitting process, it cannot override zoning restrictions. Fire department approval is typically part of the building permit review process, which can only occur after zoning compliance is established.

Option D: Apply for a building permit with the current zoning

Beginning construction without proper zoning approval and permits is illegal and would result in stop-work orders, fines, and potential demolition requirements. All zoning and permitting must be completed before construction begins.

Memory Technique

Use the acronym 'ZAP' - Zone first, Apply for permits, then Proceed with construction. Never skip the zoning step!

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, and local zoning ordinance sections on non-conforming uses and variance procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.