You receive shop drawings for custom millwork that show different wood species than specified. The architect has not yet reviewed these drawings. What is your appropriate action?

Correct Answer

B) Forward to architect for review and approval of substitution

Material substitutions require architect/engineer approval. Shop drawings with substitutions should be forwarded for design professional review before contractor action.

Answer Options
A
Reject the drawings immediately
B
Forward to architect for review and approval of substitution
C
Install as shown and document the change
D
Approve the drawings if the wood species is equivalent

Why This Is the Correct Answer

Material substitutions require architect/engineer approval. Shop drawings with substitutions should be forwarded for design professional review before contractor action.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.