EstatePass
Project MgmtBlueprintsmedium17% of exam part

You discover a discrepancy between the architectural plans showing a 6-inch concrete slab and the structural drawings showing an 8-inch slab. What is the most appropriate first action?

Correct Answer

A) Submit a Request for Information (RFI) to the design team

When discrepancies exist between different drawing sets, the proper procedure is to submit an RFI to the design team for clarification. This ensures proper documentation and prevents potential liability issues.

Answer Options
A
Submit a Request for Information (RFI) to the design team
B
Follow the architectural plans since they show the finished floor
C
Use your best judgment and install the 8-inch slab
D
Follow the structural drawings since they govern structural elements

Why This Is the Correct Answer

Submitting an RFI is the proper protocol when discrepancies exist between different drawing sets. This creates a documented trail of communication with the design team and ensures the contractor receives official clarification before proceeding. Making assumptions or choosing one drawing over another without clarification can lead to costly mistakes, rework, and potential liability issues. The RFI process protects all parties and ensures the work is performed according to the design team's intent.

Why the Other Options Are Wrong

Option C: Use your best judgment and install the 8-inch slab

While structural drawings typically govern structural elements, automatically following them without clarification ignores proper communication protocols. There may be valid reasons for the discrepancy that only the design team can explain, and proceeding without an RFI bypasses necessary documentation.

Option D: Follow the structural drawings since they govern structural elements

Using personal judgment to resolve drawing discrepancies is inappropriate and potentially dangerous. Contractors should never make design decisions without proper authorization from the design team, as this can create liability issues and may not meet the project's actual requirements.

Memory Technique

RFI = 'Resolve First, Install' - always resolve discrepancies before installation

Reference Hint

Florida Building Code, Chapter 1 - Administration and Enforcement, sections on construction documents and plan discrepancies

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.