A contractor receives shop drawings for structural steel that show connections different from those indicated in the contract documents. The shop drawings are stamped by a licensed engineer. What should the contractor do?
Correct Answer
B) Submit the shop drawings to the architect/engineer for review and approval
Shop drawings must be submitted to the design team for review and approval regardless of engineering stamps. The design team needs to verify compatibility with the overall design intent and coordinate with other building systems.
Why This Is the Correct Answer
Shop drawings must always be submitted to the architect/engineer for review and approval, even when stamped by a licensed engineer. The design team needs to verify that any changes are compatible with the overall structural design, building systems, and project specifications. The engineer's stamp on shop drawings indicates the fabricator's engineer has reviewed the connections, but it doesn't replace the need for design team approval. This process ensures coordination with other trades and maintains the design intent of the original contract documents.
Why the Other Options Are Wrong
Option A: Fabricate according to the original contract documents
Simply proceeding with fabrication because drawings are engineer-stamped bypasses the required review process and could lead to conflicts with other building systems or design intent, potentially resulting in costly rework or safety issues.
Option C: Proceed with fabrication since the shop drawings are engineer-stamped
Fabricating according to original contract documents ignores potentially necessary or beneficial changes shown in the shop drawings, and fails to follow proper submittal procedures required in construction administration.
Option D: Request the steel fabricator to revise the drawings to match contract documents
Requesting revisions without first submitting for review assumes the changes are unacceptable, when they may actually be improvements or necessary modifications that the design team would approve.
Memory Technique
Think 'STAMP doesn't SKIP' - even if shop drawings have an engineer's stamp, you can't skip the submittal process to the design team.
Reference Hint
AIA A201 General Conditions, Section 3.12 - Shop Drawings, Product Data and Samples
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
You are reviewing a site plan for a commercial project. The plan shows a fire lane with a width of 18 feet. According to typical Florida fire codes, is this width adequate?
Next Question
You discover a discrepancy between the architectural plans showing a 6-inch concrete slab and the structural drawings showing an 8-inch slab. What is the most appropriate first action?
