You are estimating concrete for a foundation that measures 120' × 80' × 2' thick. Including 8% waste factor, how many cubic yards of concrete should you order?

Correct Answer

A) 768 cubic yards

Volume = 120' × 80' × 2' = 19,200 cubic feet. Convert to yards: 19,200 ÷ 27 = 711.11 cubic yards. With 8% waste: 711.11 × 1.08 = 768 cubic yards.

Answer Options
A
768 cubic yards
B
924 cubic yards
C
711 cubic yards
D
855 cubic yards

Why This Is the Correct Answer

Option B correctly follows the complete calculation process for concrete estimation. First, the volume is calculated in cubic feet (120' × 80' × 2' = 19,200 cf), then converted to cubic yards by dividing by 27 (19,200 ÷ 27 = 711.11 cy). Finally, the 8% waste factor is applied by multiplying by 1.08 (711.11 × 1.08 = 768 cubic yards). This accounts for both the unit conversion and the industry-standard waste allowance.

Why the Other Options Are Wrong

Option C: 711 cubic yards

Option A represents only the base concrete volume without the waste factor applied (711 cubic yards). This would result in insufficient concrete for the project since it doesn't account for the 8% waste that typically occurs during mixing, transport, and placement.

Option D: 855 cubic yards

Option C appears to use an incorrect waste factor calculation, possibly applying 20% waste (711 × 1.20 = 853) instead of the specified 8%. This would result in over-ordering concrete and unnecessary cost.

Memory Technique

Remember '27 CUBES' - there are 27 cubic feet in 1 cubic yard (3×3×3). For waste factors, think 'W + 1' where W is the decimal waste (0.08 + 1 = 1.08 multiplier).

Reference Hint

Florida Building Code Chapter 19 (Concrete) or construction estimating references covering concrete volume calculations and waste factors

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.