You are estimating concrete for a foundation that measures 120' × 80' × 2' thick. Including 8% waste factor, how many cubic yards of concrete should you order?
Correct Answer
A) 768 cubic yards
Volume = 120' × 80' × 2' = 19,200 cubic feet. Convert to yards: 19,200 ÷ 27 = 711.11 cubic yards. With 8% waste: 711.11 × 1.08 = 768 cubic yards.
Why This Is the Correct Answer
Option B correctly follows the complete calculation process for concrete estimation. First, the volume is calculated in cubic feet (120' × 80' × 2' = 19,200 cf), then converted to cubic yards by dividing by 27 (19,200 ÷ 27 = 711.11 cy). Finally, the 8% waste factor is applied by multiplying by 1.08 (711.11 × 1.08 = 768 cubic yards). This accounts for both the unit conversion and the industry-standard waste allowance.
Why the Other Options Are Wrong
Option C: 711 cubic yards
Option A represents only the base concrete volume without the waste factor applied (711 cubic yards). This would result in insufficient concrete for the project since it doesn't account for the 8% waste that typically occurs during mixing, transport, and placement.
Option D: 855 cubic yards
Option C appears to use an incorrect waste factor calculation, possibly applying 20% waste (711 × 1.20 = 853) instead of the specified 8%. This would result in over-ordering concrete and unnecessary cost.
Memory Technique
Remember '27 CUBES' - there are 27 cubic feet in 1 cubic yard (3×3×3). For waste factors, think 'W + 1' where W is the decimal waste (0.08 + 1 = 1.08 multiplier).
Reference Hint
Florida Building Code Chapter 19 (Concrete) or construction estimating references covering concrete volume calculations and waste factors
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor includes an indemnification clause requiring the subcontractor to defend and hold harmless the contractor from any claims arising from the subcontractor's work. This type of clause is:
Next Question
In quality control procedures, what is the primary purpose of implementing a punch list process?
